Ongoing Projects

Reconstruction, Upgrade, Development, and Operation of Bandar Abbas Wastewater Treatment Plant and Main Pumping Station (EPC Method)

The project includes:

  • Reconstruction of the existing wastewater treatment plant while maintaining its operation
  • Increasing treatment capacity from 65,000 cubic meters to 100,000 cubic meters
  • Renovation and capacity upgrade of the main wastewater pumping station in Bandar Abbas
  • Operation and maintenance of facilities for 36 months after the construction phase
Project Progress
Completed 82.14%

Construction of Advanced Wastewater Treatment and Desalination Facilities

The project includes:

  • Engineering services for project design
  • Construction of advanced treatment and desalination buildings, including DAF units, sand filters, RO and UF units, etc.
  • Procurement, transportation, installation, and commissioning of electromechanical equipment for various project units
  • Operation of the facility for two years
Project Progress
Completed 47.88%

Construction of a Water Storage Reservoir in the Northern Site of the Persian Gulf Special Economic Zone for Mining and Metal Industries

The project includes:

  • Construction of a 40,000 cubic meter water storage reservoir in the development site of the Persian Gulf Special Economic Zone
  • Construction of auxiliary buildings, including security, administrative, and chlorination facilities
  • Procurement, transportation, installation, and commissioning of electromechanical equipment, including pipes, valves, fittings, chlorination equipment, etc.
  • Construction of an access road, perimeter wall, and landscaping
Project Progress
Completed 99.09%

Construction of the Treated Wastewater Distribution Network in the Persian Gulf Special Economic Zone

  • Procurement phase:
    • Supply of 22 km of pipelines with diameters ranging from 450 mm to 1200 mm (polyethylene and steel)
    • Supply of valves, fittings, and related accessories
  • Implementation phase:
    • Installation of 22 km of steel and polyethylene pipelines (450 mm to 1200 mm)
    • Construction of 80 valve chambers and approximately 430 meters of pipe jacking
    • Construction of a 15 km service road
Project Progress
Pipe Supply 100%
Execution
Completed 76%

Procurement, Construction, Installation, and Commissioning of Equipment for the Wastewater Recycling Pumping Station in Bandar Abbas

The project includes:

  • Procurement, transportation, installation, and commissioning of:
    • Five pumps, each with a capacity of 1,250 cubic meters per hour and 142-meter head
    • Three power transformers with a capacity of 250 KVA
    • One 10-ton six-function overhead crane
Project Progress
Completed 90%

Expansion and Rehabilitation of Wastewater Collection Networks to Reduce Salinity and Sand Infiltration

The project includes:

  • Financing the expansion and rehabilitation of the sewage collection network in neighborhoods near Khur Goorsuzan (Chahestaniha, beltways, and Ayatollah Ghafari)
  • Installation of polyethylene pipelines with diameters ranging from 200 mm to 600 mm
Project Progress
Completed 28%
Scroll to Top